As part of the ongoing Breakwater strengthening project, we have made significant progress in 2024. This year, we planned to place about 630 Akmon concrete units on the breakwater. So far, approximately 330 units have been installed during phase one, in September.
We’re now gearing up for phase two, which will begin on Saturday 7, December through to Friday, 20 December. This final round will focus primarily on the northern end of the breakwater and is expected to cause minimal disruption to port traffic. Unlike phase one, there will be no road closures; however, traffic management measures will be in place intermittently to ensure safety and efficiency.
With this round of placement largely concentrated at the northern end, we anticipate even less disruption to daily port operations compared to the previous phase. The port’s traffic planning team and all relevant stakeholders have been fully briefed on the schedule and logistics, ensuring seamless coordination throughout the project’s final phase. |